What construction project management software is for
Construction project management software, for a main contractor or a larger specialist contractor, has to hold three things across every live project, time, change and information. Time is the programme and progress against it. Change is every instruction, early warning, compensation event and variation, each with dates the contract sets. Information is the design detail the site is waiting on and the subcontract packages that must be let before their trades are due. On one project a good project manager can hold all of it in spreadsheets. With several projects on different sites, the directors cannot see which job is drifting until the monthly report, and a notice missed on one of them can cost money the programme never shows. A contractor running many smaller jobs from enquiry to invoice is better served by our construction job management software. The money side, valuations, retention and cost value reconciliation, belongs to the commercial ledger, which this system feeds rather than replaces.
The programme stays in the planning package your planners already use, such as Asta Powerproject or Microsoft Project, and its activities are imported where the package can export them, so site managers get a look-ahead of the coming weeks drawn from the master instead of redrawn by hand. Progress is recorded against activities from site, while the daily diary and snag lists stay with the site team’s own tools. Each subcontract package carries the date it must be let by, its lead time and its start on site, so a package still out to tender close to its start date shows up early, with the firms themselves vetted in subcontractor management software. Requests for information and technical queries carry the date an answer is needed to hold the programme, the consultant each sits with and the packages it affects, and an information required schedule goes to the design team from the same record.
Change, notices and the contract’s clock
The change register is the heart of it. Instructions, early warnings, compensation events, variations and notices of delay are logged against the project, with the periods for notification, quotation and reply entered from the contract, and the register shows what falls due this week across every job. Those periods differ by form of contract and by amendment. The standard NEC4 Engineering and Construction Contract gives the contractor eight weeks from becoming aware of a compensation event to notify it, and a late notice can cost the entitlement. JCT building contracts expect the contractor to give notice once it becomes reasonably apparent that progress is being or is likely to be delayed. Many contracts change these terms, so the system tracks the dates you enter, and what they mean for a given event is for you and your advisers. Each change item carries its value by stage, notified, quoted, assessed and agreed, which gives the commercial team the change element of the forecast final account without a separate spreadsheet.
Where bespoke fits, and what it costs
Packaged construction management software covers drawings, site forms and project records, and plenty of contractors run on it without needing anything built. The case for a build is narrower, the join between the change the site logs, the forecast the commercial team reports and the view the directors need across every job, whether that sits beside a platform you keep or replaces the spreadsheets around it. Cost follows the number of registers and how deeply the system connects to the rest, and our bespoke software cost guide explains how a fixed quote is built.
If each project keeps its own change spreadsheet and the directors see them once a month, contact us or call 01202 237027 for a free consultation.